Fire Hydrant Block Plans

 

The information contained on this plan is required by the responding emergency services & displayed on an engraved external plate outside the building

This requires specialist knowledge & information should only be supplied by system installation or maintenance engineers. Refer to AS2419

The layout should show an outline of the site buildings, the fire hydrant outlets, (single or double)

Fire hose reel locations, size of connecting pipe work & position of isolating or non-return valves, booster outlets etc, and main electrical switchboard & gas isolation valves.

Name of installation contractors, operational test /discharge pressures, and the height of highest hydrant relative to the lowest booster inlet